Horizon I Projects
|
|
Project Type
|
Useful life
|
Expected Commission
Date
|
Capacity
MW
|
|
|
Hydro -
|
|
|
|
|
2
|
Kiambere optimisation
|
50
|
1 April 2009
|
20
|
|
3
|
Tana Development
|
50
|
1 April 2010
|
20
|
|
4
|
Raising of Masinga Dam
|
50
|
April 2012
|
15
|
|
5
|
Kindaruma 3rd Unit
|
50
|
October 2012
|
25
|
|
6
|
Sangoro
|
50
|
1 Oct 2011
|
21
|
|
|
Geothermal-
|
|
|
|
|
1
|
Olkaria II 3rd Unit
|
25
|
1 July 2010
|
35.0
|
|
2
|
Eburu 2.5 MW
|
25
|
1 Jan 2011
|
2.5
|
|
3
|
Olkaria IV - New
|
25
|
1 Jan 2013
|
140
|
|
4
|
Olkaria I - New Plant
|
25
|
1 Jan 2013
|
70
|
|
5
|
Olkaria - Life Extension
|
25
|
1 Jan 2013
|
70
|
|
|
Thermal-
|
|
|
|
|
1
|
Thermal Plant - 120MW
|
20
|
1 Oct 2010
|
120
|
|
|
Wind-
|
|
|
|
|
1
|
Ngong wind
|
25
|
1 Aug 2009
|
5.1
|
|
|
|
|
|