8.6MW Gogo Hydro Power Plant Redevelopment Project

Project Details

Promoter:

Kenya Electricity Generating Company (KenGen) PLC

Private sector participation:

Implementing Consultant and EPC Contractor

Status:

Consultant procured; D&B procurement in progress.

Location:

Migori County

Know More About This Project

The project entails redevelopment and expansion of existing 2 Gogo Hypro powerplant along River Kuja in Nyatike, Migori County.

This will involve desilting of the existing reservoir, Rehabilitation of the existing dam structure, construction of a new powerhouse that will house 2 × 4.3 MW Kaplan turbines and construction of a new substation.

Upon competition, the project is expected to positively impact grid stability in Western Kenya Region.