Olkaria I Power Station was the first geothermal power plant in Africa. The 45 MW plant was commissioned in three phases and has three units each generating 15MW of electricity. The first unit was commissioned in June 1981, the second and third units in November 1982 and March 1985, respectively. The second phase of Olkaria I was commissioned in 2010 . The plant has had an average availability factor of over 95 per cent from commissioning. The power generated is connected to the national grid via a 132KV-transmission line.

 