• 0711036000
  • Mon - Thur 07:45 - 17:00 (Fri 07:45 - 16:30)
  • KenGen Pension Plaza II

Nairobi, June 10th, 2021: Leading energy producer, Kenya Electricity Generating Company PLC (KenGen) has started installing a Steam Turbine into the Olkaria 1 AU 6 Power Plant, signaling a major breakthrough in the on-going construction of the power plant.

This is a great achievement, given that the Steam Turbine is the heart of the power plant. It is the component that is usually rotated to drive the generator that produces electricity.

KenGen Managing Director and CEO, Mrs, Rebecca Miano said the installation of the turbine’s lower casing starts today, Thursday 10th June 2021.

“This is the largest single unit of turbine we will be installing in any of our power plants with a capacity of 83.3MW and with its installation we are now entering the final phase of construction of the power plant,” Mrs. Miano said.

She further revealed that this was the first time a Fuji Turbine was being installed not only in Kenya but in Africa.

Fuji Electric who is the Turbine Manufacturer has deployed Technical Adviser who will oversee the whole installation process and ensure success. He will be assisted a team of Engineers from both Fuji Electric and KenGen.

The turbine installation and its auxiliaries will take approximately three (3) months including dynamic balancing. This Installation will run alongside other major installations such as Generator Step Up Transformer (GSUT), Auxiliary transformers, MV and LV Switchgears, Non Condensable Gas extraction system, Cooling water system, Air Compressor system, Heating and Ventilation system and Emergency Diesel Generator.

Mrs. Miano said KenGen is happy with the progress of the project as it is on schedule despite challenges brought about by the COVID-19 pandemic. “With these activities running concurrently, it will ensure that the power plant’s commissioning is achieved in the last quarter of the year 2021,” she added.

In January this year, a team of 15 engineers and experts in heavy lifting successfully mounted a generator weighing 99 tonnes (99,000 kilograms) onto the power plant’s Steam Turbine in Olkaria, Naivasha. Upon completion, the power plant will generate 83.3MW of electricity which will be injected into the national grid.

The generator which is worth Ksh 600 million was manufactured by Fuji Electric of Japan. It took five days to transport it from Mombasa to Olkaria with several stops along the way owing to its size.

Construction of Olkaria 1 AU 6 geothermal power plant started in December 2018 following a ground-breaking ceremony which was graced by President Uhuru Kenyatta.

The construction of the additional power plant is aligned to the company’s long-term strategy and the Least Coast Power Development Plan (LCPDP) focused on sustainable supply of renewable energy in support of the Government Big Four Agenda.

Currently, KenGen supplies about 72% of the electricity consumed in Kenya, with over 80% of this coming from renewable sources. The company has a total installed generation capacity of 1,818MWcomprising hydro (826MW) geothermal (713MW) thermal (254MW) and wind (26MW).

Ends....

ft Featured Video

ftAwards

Group 585
Group 586
Group 587
Group 581
 
 
 

ftOur Contacts

Head Office

  • KenGen Pension Plaza II
    Kolobot Road, Parklands
  • P. O. BOX 47936, 00100, Nairobi
  • TEL:
  • +254 711 036-000
  • +254 732 116-000
  • +254 020 366-6000
  • Email: [email protected]

© 2024 KenGen